View the construction risk assessment example ↓
Why might a main contractor ask for your risk assessment?
“Please send your risk assessment before you arrive.” The main contractor wants to understand your work, who could be affected and how it fits around the site.
Assessing and controlling work-related risks is a health and safety duty, not simply a client paperwork request. HSE says employers with five or more employees must record significant findings. A contractor may also require written assessments through site rules or contract terms, including from smaller firms. Those submission requirements are separate from the underlying duty to manage risks.
Confirm the requested format, scope and submission deadline. Acceptance by a client does not prove the work is safe: the controls still need to be put into practice.
Construction risk assessment example — a small refurbishment job
- Project
- Commercial office refurbishment
- Activity
- Partition and shelving installation
- Personnel
- Two operatives
- Status
- Illustrative example — not approved for site use
Adjacent offices remain occupied, with deliveries and access shared with other trades. The five activities below cover handling, drilling, tool use, elevated fixing and working beside occupants.
This is not a completed assessment authorising work. A competent person must adapt it to the actual materials, equipment, people and site, closing unresolved checks before affected work starts.
Initial ratings are illustrative, not HSE-approved scores. Apply your organisation's risk matrix consistently if used. Assess residual risk after checking controls, not automatically as “low”. Replace role titles with named people.
| Work activity | Principal hazard | Key control measures |
|---|---|---|
| Moving boards and materials | Heavy or awkward loads; obstructed routes | Avoid hazardous carrying; use handling aids and clear delivery routes; assess unavoidable lifts. |
| Drilling and cutting | Dust, flying fragments and concealed services | Confirm asbestos and services information; control dust at source; restrict access and assess protective equipment. |
| Using portable power tools | Moving blades, damaged equipment, noise and vibration | Use suitable tools and trained users; check guards and condition; control noise and vibration exposure. |
| Fixing above head height | Falls and dropped tools or materials | Avoid height work where possible; select suitable access and fall protection; secure materials and exclude people below. |
| Working beside occupied offices | People entering the work area; obstructed exits | Segregate work and deliveries; keep escape routes clear; coordinate tasks and maintain housekeeping. |
- Hazard
- Heavy or awkward loads; obstructed routes
- Who might be harmed and how
- Operatives: back or muscle injuries, trapped fingers; others: trips.
- Initial risk assessment
- Medium — repeated handling and restricted access.
- Suitable control measures
- Avoid hazardous carrying where practicable. Use suitable handling aids, arrange deliveries near the work area and keep routes clear. Assess unavoidable lifts; plan team handling where appropriate.
- Further actions and responsible persons
- Working supervisor: confirm delivery route, handling aids and load assessment before unloading.
- Residual risk
- Lower if verified; reassess awkward loads or access changes.
- Hazard
- Dust, flying fragments and concealed services
- Who might be harmed and how
- Operatives and nearby occupants: respiratory harm or eye injuries; operatives: electric shock from damaged services.
- Initial risk assessment
- High — dusty work and unconfirmed service locations.
- Suitable control measures
- Check asbestos information before disturbing materials; confirm services and required isolation. Reduce dust at source with suitable extraction or suppression. Restrict access; select eye protection and suitable RPE where the assessment requires it, including face-fit testing for tight-fitting RPE.
- Further actions and responsible persons
- Site manager: confirm material and service information. Supervisor: check dust controls before drilling; stop if information is uncertain.
- Residual risk
- Reassess after checks; do not start with unresolved asbestos or service risks.
- Hazard
- Moving blades, damaged equipment, noise and vibration
- Who might be harmed and how
- Operatives: cuts, electric shock, hearing damage or vibration-related harm.
- Initial risk assessment
- High — repeated tool use close to others.
- Suitable control measures
- Select suitable equipment and trained users. Check guards, accessories and electrical condition. Assess noise and vibration exposure; choose lower-exposure methods and limit exposure. Provide assessed protective equipment, not PPE as the only control.
- Further actions and responsible persons
- Working supervisor: check equipment, usage time and exposure controls before use.
- Residual risk
- Review after controls; depends on equipment and actual exposure.
- Hazard
- Falls and dropped tools or materials
- Who might be harmed and how
- Operatives: serious fall injuries; people below: struck by falling objects.
- Initial risk assessment
- High — elevated work and occupied areas nearby.
- Suitable control measures
- Avoid height work where possible; otherwise use suitable access equipment with collective fall protection where practicable. Check floor conditions and equipment. Secure materials and exclude people below. Do not default to a ladder without assessing suitability.
- Further actions and responsible persons
- Working supervisor: select and check access equipment and exclusion area before elevated work.
- Residual risk
- Lower only once arrangements are confirmed; review if reach or access changes.
- Hazard
- People entering the work area; obstructed exits
- Who might be harmed and how
- Occupants, visitors and other trades: trips, collisions or delayed escape.
- Initial risk assessment
- Medium — shared circulation routes.
- Suitable control measures
- Agree segregated work and delivery areas with the site manager. Maintain escape routes, control trailing leads and waste, and coordinate disruptive tasks with other trades and occupants.
- Further actions and responsible persons
- Site manager: agree segregation and emergency routes before setup. Supervisor: check housekeeping throughout the shift.
- Residual risk
- Lower if separation holds; stop and review if occupants enter the work zone.
These controls draw on the HSE guidance linked below. Dust controls need a task-specific COSHH assessment where applicable; a general risk assessment does not replace it. Check asbestos information is suitable for the planned refurbishment before disturbing the building fabric. Unknown materials are a reason to stop and obtain advice, not guess.
How to adapt the example to your own construction site
Walk the area with someone who understands the site. Check access, floors, services, deliveries, emergency arrangements and who works nearby. Review the actual tools, materials and access equipment.
Consider competence and individual needs. Discuss controls with operatives: they may spot handling or reach problems the drawing misses. Agree coordination with other contractors.
Replace the example entries with your findings. Our risk assessment template guide covers the blank structure.
What should you check before submitting a risk assessment?
Before sending it, check that a site supervisor can identify the work and required actions:
- Correct site address, contractor details, assessor and document date.
- An accurate scope: tasks included, exclusions and work boundaries.
- Relevant hazards, people at risk and specific, workable controls.
- Site-specific access, services, occupants and other contractors considered.
- Further actions with named responsible people and completion deadlines.
- Review triggers, version details and worker briefing or sign-off arrangements.
- Any method statement, COSHH assessment or other documents the client requests.
Send the current version for site review. Resolve questions before affected work begins and brief the team. A signature records acknowledgement; it does not replace understanding.
Do you need a method statement as well?
A risk assessment identifies hazards, who could be harmed and the controls needed. A method statement explains the safe sequence of work: setup, equipment, task steps, checks and handover. RAMS brings the risk assessment and method statement together.
Construction teams often prepare them together so the working method matches the assessed controls. A standalone method statement or combined RAMS document is not universally required by law for every task; particular work can have specific planning requirements, and the client may request both documents. Check what applies to your job.
Use our method statement guide for the sequence and our RAMS template guide for the combined format. For roof work, the roofing RAMS and risk assessment example addresses a different set of hazards; do not carry refurbishment controls over unchanged.
Common reasons risk assessments need revising
Replace “wear PPE” or “take care” with practical arrangements: which equipment, which work area, what check and who is responsible. Missing site information and unfinished actions leave readiness unclear.
Revise the assessment when the scope, access, equipment, personnel or surrounding work changes, or when controls are not working. Worker feedback, an incident or a near miss may reveal a gap. Stop affected work where necessary, agree revised controls and communicate the update before restarting. Keep the current version available, not just the original email attachment.
Create and share a site-specific risk assessment with Graftly
Graftly guides you through creating a site-specific risk assessment, reviewing and updating your document, saving it and exporting a PDF to share with your client or site team.
Keep your reviewed document current as conditions change. Our RAMS software guide explains the wider document workflow.
Official HSE guidance
HSE guidance covers Great Britain. For work in Northern Ireland, check the relevant HSENI requirements and guidance as well.